How Long Does a House Rewire Take? A Realistic Timeline

By Emergency Electrician Bath · Published · Updated

Electrician fault finding at a consumer unit with test meters

A full rewire of a typical three-bedroom house usually takes around five to ten working days, but the time depends on the size of the property, access, the type of walls and whether the home is occupied. This guide explains the stages of a rewire, typical timescales for different Bath properties, and how to keep disruption to a minimum.

Typical Timescales

Property First fix Second fix Total (approx.)
One-bedroom flat 2 to 3 days 1 day 3 to 4 days
Two-bedroom terrace 3 to 5 days 1 to 2 days 4 to 7 days
Three-bedroom house 5 to 7 days 2 days 7 to 10 days
Four or more bedrooms 7 to 10 days 2 to 3 days 10 to 14 days
Large Georgian townhouse 10 days or more 3 days or more 2 to 4 weeks

These are working days for a small team. Plastering and decorating are extra.

The Stages of a Rewire

1. Survey and Planning

The electrician inspects the property, agrees socket and light positions and plans cable routes.

2. First Fix

Floorboards are lifted, channels cut in walls and new cables run to every point. The old wiring stays live where possible until the new is ready.

3. Plastering

Channels are filled and walls repaired.

4. Second Fix

Sockets, switches, lights and the consumer unit are fitted.

5. Testing and Certification

Every circuit is tested and an Electrical Installation Certificate issued. The work is notified under Part P. See electrical certificates after work explained.

What Affects the Time

  • Access: furniture, fitted carpets and floor coverings slow the work.
  • Wall type: solid stone and lime plaster take longer than stud walls. See rewiring old lime plaster walls.
  • Listed status: listed buildings may need careful routes and consent. See rewiring listed buildings in Bath.
  • Occupancy: an empty house is quicker.
  • Extras: smoke alarms, data cabling, outdoor circuits and EV chargers add time.

Living at Home During a Rewire

It is possible but disruptive. Power can usually be restored at the end of each day. See can you stay home during a rewire?

Reducing Disruption

  1. Clear rooms in advance.
  2. Agree a room-by-room plan.
  3. Lift carpets if possible.
  4. Book plastering early.
  5. Plan for dust.

Is a Rewire Needed?

Not every old installation needs a full rewire. An EICR shows the true condition. See signs your house needs a rewire.

Frequently Asked Questions

Can I live without power during a rewire?

You usually have power at night. Some days may have longer outages.

Does a rewire include plastering?

Usually only filling channels. Full plastering is separate.

Do I need to move out?

Not usually, but an empty house is quicker.

How long does a partial rewire take?

Often one to three days per floor or area.

Planning a Rewire?

Contact us for a survey and timescale. See our services.

Related Electrical Guides

Fast Call-Out

Get an Emergency Electrician
Out in Bath

Call 07893 943507 and tell us what has happened: what has tripped or stopped working, whether you can smell burning, and whether water is involved. An electrician from Emergency Electrician Bath comes to your Bath property, makes it safe, finds the fault and agrees the price with you before any repair starts.

Available now Open 24 hours
✓ Fast Call-Out ✓ BS 7671 Testing ✓ Written Quotes ✓ Based in Bath